General Mathematics · Mock exam 2026 All mock exam questions
Mock exam · Paper 2 · Complex familiar

Question 4

[5 marks] Scientific calculator
Compare with past QCAA questions2024 Paper 2 Question 4 · 2021 Paper 1 Question 19
The question

A school is renovating its library. The table shows the activities involved, their duration (days) and their immediate predecessors.

ActivityDuration (days)Immediate predecessor/s
A4—
B6—
C3A
D5A
E2B, C
F7D
G4E
H3F, G

Activity C is delayed and will take 5 days longer than planned.

Use a project network diagram with completed forward and backward scanning to determine the effect of this delay on the minimum time to complete the renovation.

Watch the solution first

Scan both ways, then spend the float

The network is drawn in table order and scanned forward and backward, then the float of C is compared with the delay and the network is rescanned with C taking 8 days.

Draw each activity as an arc, in table orderB and C end at one node before E, and F and G end at one node before HForward scan, left to right: node 1 is 0, node 2 is 0 + 4 = 4Node 3: max(0 + 6, 4 + 3) = max(6, 7) = 7Node 4: 4 + 5 = 9. Node 5: 7 + 2 = 9Node 6: max(9 + 7, 9 + 4) = max(16, 13) = 16Node 7: 16 + 3 = 19, so the minimum time is 19 daysBackward scan, right to left: node 7 is 19, node 6 is 19 − 3 = 16Subtract each duration: 16 − 4 = 12, 16 − 7 = 9, 12 − 2 = 10Node 2: min(9 − 5, 10 − 3) = min(4, 7) = 4Node 1: min(4 − 4, 10 − 6) = min(0, 4) = 0EST = LST along A–D–F–H: the critical path, minimum time 19 daysLatest start of C = 10 − 3 = 7, EST 4, so the float of C = 7 − 4 = 3 daysC is delayed: it now takes 3 + 5 = 8 days. Scan againRescan with C = 8: node 3 becomes 12 | 12, node 5 becomes 14 | 14Node 6 becomes 18 | 18, node 7 21 | 21, node 4 9 | 11A–C–E–G–H is now the critical path, 21 daysDelay of 5 days exceeds the float of 3 days by 2 days.Minimum time increases from 19 days to 21 days.A, 4B, 6C, 3C, 8D, 5E, 2F, 7G, 4H, 3004471210129911914121416181618192119216716134704latest start 10 − 3 = 7float 7 − 4 = 3Mark 1Mark 2Mark 3Mark 4Mark 5
Now for the mathematics

Delay activity C and watch the scans rerun

Drag the slider to delay C by 0 to 6 days. Every node shows EST | LST, and thick arcs have zero float.

|||||||A, 4B, 6D, 5E, 2F, 7G, 4H, 3

Each node shows EST | LST (days). Values that differ from the planned scan are bold.

Try a common error

Marked wrong.

Marking guide · 5 marks

Work through the solution one mark at a time

Try each step yourself before you reveal it.

Choose a method

Step 11 mark

Draw the network with each activity as an arc between two events: seven nodes and eight arcs, each labelled with its activity and duration. E follows both B and C, so B and C end at the same node. H follows both F and G, so F and G end at the same node.

1234567A, 4B, 6C, 3D, 5E, 2F, 7G, 4H, 3

Nodes numbered 1 to 7 here for reference.

Why?

The network shows every activity as an arc between events, so the scans can follow the dependencies.

Marking

Completing the forward scan with a duration of 8 days for activity C to find a new minimum time of 21 days is an alternative method. Method 2 shows that route.

Marker: correctly constructs the project network diagram showing all 8 activities with their durations and dependencies

Step 21 mark

Forward scan, left to right. Where arcs meet, take the largest value.

$$\begin{aligned}\text{Node 1: }&0\\\text{Node 2: }&0+4=4\\\text{Node 3: }&\max(0+6,\ 4+3)=\max(6,7)=7\\\text{Node 4: }&4+5=9\\\text{Node 5: }&7+2=9\\\text{Node 6: }&\max(9+7,\ 9+4)=\max(16,13)=16\\\text{Node 7: }&16+3=19\end{aligned}$$

The minimum time to complete the renovation is 19 days.

Why?

The forward scan gives each event its earliest start time. Every arc into a node must be finished, so the largest value is kept where arcs meet.

Marker: completes forward scanning

Step 31 mark

Backward scan, right to left. Where arcs leave, take the smallest value.

$$\begin{aligned}\text{Node 7: }&19\\\text{Node 6: }&19-3=16\\\text{Node 5: }&16-4=12\\\text{Node 4: }&16-7=9\\\text{Node 3: }&12-2=10\\\text{Node 2: }&\min(9-5,\ 10-3)=\min(4,7)=4\\\text{Node 1: }&\min(4-4,\ 10-6)=\min(0,4)=0\end{aligned}$$

0|04|47|109|99|1216|1619|19A, 4B, 6C, 3D, 5E, 2F, 7G, 4H, 3

Each node shows EST | LST (days).

Critical path: A–D–F–H (EST $=$ LST at every node on it), minimum time 19 days.

Why?

The backward scan gives each event its latest start time. The smallest value is kept where arcs leave, so no later activity is delayed.

Marking

An alternative representation, for example ESTs and LSTs shown in a table beside the diagram, also earns the scanning marks.

Marker: completes backward scanning

Step 41 mark

C starts at node 2 (EST 4) and ends at node 3 (LST 10), so the latest start time of C is $10-3=7$.

$$\text{Float of C}=\text{LST}-\text{EST}=7-4=3\text{ days}$$

Why?

The float of C is how long C can be delayed without delaying the project.

Marking

Follow-through applies from an error in earlier working.

Marker: determines the float time for activity C

Step 51 mark

The delay of 5 days exceeds the float of 3 days by $5-3=2$ days.

$$19+2=21\text{ days}$$

The new critical path is A–C–E–G–H ($4+8+2+4+3=21$).

Why?

Only the part of the delay beyond the float adds to the minimum time.

Marking

An equivalent statement, for example “The renovation will take 21 days.”, also earns this mark.

The delay to activity C increases the minimum time to complete the renovation by 2 days, from 19 days to 21 days.

Marker: determines the effect of the delay on the minimum time

Step 11 mark

Give C its delayed duration, $3+5=8$ days, and draw the same network as in Method 1 with arc C labelled C, 8.

1234567A, 4B, 6C, 8D, 5E, 2F, 7G, 4H, 3

Nodes numbered 1 to 7 here for reference.

Marker: correctly constructs the project network diagram showing all 8 activities with their durations and dependencies

Step 21 mark

Forward scan with C $=8$. Where arcs meet, take the largest value.

$$\begin{aligned}\text{Node 1: }&0\\\text{Node 2: }&0+4=4\\\text{Node 3: }&\max(0+6,\ 4+8)=\max(6,12)=12\\\text{Node 4: }&4+5=9\\\text{Node 5: }&12+2=14\\\text{Node 6: }&\max(9+7,\ 14+4)=\max(16,18)=18\\\text{Node 7: }&18+3=21\end{aligned}$$

Marker: completes forward scanning

Step 31 mark

Backward scan with C $=8$. Where arcs leave, take the smallest value.

$$\begin{aligned}\text{Node 7: }&21\\\text{Node 6: }&21-3=18\\\text{Node 5: }&18-4=14\\\text{Node 4: }&18-7=11\\\text{Node 3: }&14-2=12\\\text{Node 2: }&\min(11-5,\ 12-8)=\min(6,4)=4\\\text{Node 1: }&\min(4-4,\ 12-6)=\min(0,6)=0\end{aligned}$$

0|04|412|129|1114|1418|1821|21A, 4B, 6C, 8D, 5E, 2F, 7G, 4H, 3

Each node shows EST | LST (days).

Marker: completes backward scanning

Step 41 mark

The latest start time of C is $12-8=4$, so the float of C is $4-4=0$ days. C is now critical, on the new critical path A–C–E–G–H.

$$\text{Float of C}=4-4=0\text{ days}$$

Why?

With the delay, the float of C shows whether C now controls the project.

Marker: determines the float time for activity C

Step 51 mark

The planned minimum time is the length of the longest path A–D–F–H, $4+5+7+3=19$ days. The minimum time increases from 19 days to 21 days.

$$21-19=2\text{ days}$$

Why?

The effect is the change from the planned minimum time.

Marking

An equivalent statement, for example “The renovation will take 21 days.”, also earns this mark.

The delay increases the minimum time to complete the renovation by 2 days, to 21 days.

Marker: determines the effect of the delay on the minimum time

Common errors

If I had to guess where you might lose marks…

  • Taking the smaller value at node 3 in the forward scan: EST 6 instead of 7. The minimum time still comes out as 19, which hides the slip, but it loses Mark 2. With the delay, the same slip gives $\min(6, 12) = 6$ and “no effect, still 19 days”, which loses Mark 5 as well.
  • Taking the larger value at node 2 in the backward scan: $\max(9 - 5,\ 10 - 3) = 7$ instead of 4. This loses Mark 3.
  • Working out the float of C as the LST of node 3 minus the EST of node 2, $10 - 4 = 6$, which forgets the 3-day duration of C. A delay of 5 days then looks absorbed (“no effect”), which loses Marks 4 and 5.
  • Adding the whole delay to the project: $19 + 5 = 24$ days. This loses Mark 5.
  • Rescanning with C as 5 days instead of $3 + 5 = 8$ days. The minimum time stays at 19 days, which loses Mark 5.

Only mark this done when you could do it without help. Reading the solution does not count.

Back to the index